2019 Asphalt Overlay Project

   

Construction Updates

Bi-weekly Project Update

 

Proposed Improvements

The City of Federal Way Asphalt Overlay is an essential street maintenance program in which selected streets are repaved along with the repair and improvement to curb, sidewalks and curb ramps to meet Americans with Disabilities Act (ADA) requirements.

 

Schedule

The construction contract includes Schedules A1, A2, B and C.  Construction begins April 8, 2019 and is expected to be completed by July 31, 2019.

2019 Asphalt Overlay Schedules

  • Schedule A1:  1st Ave S – S 363rd Pl to S 361st Pl
  • Schedule A2:  1st Ave S – S 361st Pl to S 356th St
  • Schedule B:  S 336th St – 10th Pl S to 18th Ave S
  • Schedule C:  1st Ave S – SW 312th St to SW 301st St

 

Resources

2019 Asphalt Overlay Project Vicinity Map

Vicinity Map Schedules A1 and A2 – 1st Ave S – S 363rd Pl to S 356th St

Vicinity Map Schedule B – S 336th St – 10th Pl S to 18th Ave S

Vicinity Map Schedule C – 1st Ave S – SW 312th St to SW 301st St

 

More Information

2019 Asphalt Overlay Program Project Summary

Programa de colocación de carpeta asfáltica 2019

2019 아스팔트 오버레이 계획

For additional information, contact Street Systems Engineer, Jeff Huynh by email at Jeff.Huynh@cityoffederalway.com or by phone at 253-835-2721