Road Construction Updates
The following is Federal Way’s current and anticipated major street construction (6-26-20)
(Note: minor road and/or short term street impacts are not reflected here).
CURRENT WORK:
2020 Overlay Project
The City’s Contractor (Miles Resources) will be completing asphalt overlay work and sidewalk ramp upgrades in several locations. Upcoming impacts are as follows:
Hoyt Road SW – SW 326th Street to SW 320th Street:
Paving complete 6/19/20. The contractor will be raising utilities the week of June 29, 2020. There will be alternating, one-way traffic from 7:00 AM – 5:00 PM. Alternate routes encouraged.
Pete Von Reichbauer (PVR) Way – S 320th Street to S 312th Street:
Paving completed 6/4/20. Contractor will return in the middle of July to complete striping and pavement markings. Temporary lane closures will be required. Detours will be in place during the striping operations.
S 312th Street – 13th Ave S to Pacific Hwy S:
Waterline replacement work continues on this section and will continue through June. Overlay contractor will begin sidewalk and curb ramp replacement in the middle of July.
1st Ave S – S 301st Street to North City Limits:
The overlay work on this section will take place after Lakehaven completes water line and sewer replacement work. Work to begin in June.
The Ridge Subdivision (selected roads):
Paving complete 6/19/20. The Contractor will be raising utilities the week of June 29, 2020 Temporary lane closures required.
S 320th Street and Pacific Hwy – Curb Ramps: Substantially complete. Repair work required.
Dash Point Road S – 9th Place to Sacajawea Park - Sidewalks:
The City’s Contractor, Active Construction, Inc. (ACI) began construction April 6, 2020 to complete sidewalk improvements in front of Sacajawea Middle School (Dash Point Road S – 9th Place S to Sacajawea Park). Construction will restart the week of June 15 and continue through August and require temporary day time lane closures.
S 312th Street – 13th Ave S to Pacific Hwy – Watermain Replacement (Lakehaven)
Lakehaven’s contractor, HCON, will be continuing a water main replacement on S 312th Street between 13th Ave S and Pacific Hwy S ahead of the City’s overlay project. The Contractor will be working extended shifts next week from 7AM – 10 PM. Temporary lane closures will be required.
Military Road South (SR 18 to S 320th) – Pavement Patching
Starting June 8, 2020, the City’s Contractor, Pavement Maintenance, Inc. will be completing pavement patching on Military Road South between SR 18 and S 320th Street. Temporary day-time lane closures will be required.
Upcoming impacts as follows:
1st Ave S – S 301st Street to S 296th Place – Water Main and Sewer Main Replacement (Lakehaven):
Lakehaven will be replacing portions of the water and sewer lines on 1st Ave S between S 301st Street to S 296th Place. Work is anticipated to start the 2nd week of June.
For additional capital project information visit: https://www.cityoffederalway.com/streetsystems/capitalprojects