Home  /  Inside City Hall  /  Departments  /  Public Works  /  Road Construction Updates

Road Construction Updates

   

The following is Federal Way’s current and anticipated major road construction (4-26-19)

(Note: minor road and/or short term street impacts are not reflected here).

 

2019 Overlay Project – 3 locations

S 336th – 10th Ave S – 18th Ave S: Starting week of April 29 and continuing for approximately two weeks, the contractor will be completing pavement patching, grinding, and overlay. Temporary day time lane closures will be required. Expect delays. Consider alternate routes.

1st Ave S – S 368th Street to S 356th Street: Starting week of May 6 and continuing for approximately two weeks, the contractor will be completing pavement patching, grinding, and overlay. Temporary day time lane closures will be required. Expect delays. Consider alternate routes.

1st Ave S – S 312th Street to S 301st Street: Utility relocation work is on-going and will continue through middle of July. Pavement overlay work will begin after the utility relocation work is completed (mid July).

 

2018 NHS Preservation Project (Campus Drive – 19th Ave SW to 1st Ave S): Starting May 13, 2019 and taking approximately three weeks, the contractor will be completing grinding, traffic loops, and overlay (weather dependent). Multiple day time lane closures will be required. Expect delays and consider alternate routes.

 

Enchanted Parkway (SR161) Paving Project – Milton Road to S 348th Street

Washington State Department of Transportation (WSDOT) has hired Tucci and Sons to complete a paving project on Enchanted Parkway between Milton Road and S 348th Street. Contractor will be completing grinding, pavement patching, traffic signal loops, and pavement overlay through the middle of May 2019. All work will occur at night. Temporary lane closures will be required.

 

Pacific Hwy S (SR99) Paving Project – South City Limits to S 359th Street

Washington State Department of Transportation (WSDOT) has hired Tucci and Sons to complete a paving project on Pacific Hwy S from the south city limits to S 359th Street. All work will be completed at night and is scheduled to take place between middle of May through July 2019. Temporary lane closures will be required.

 

LED Street Light Conversion Project (Citywide): The City’s Contractor, Ameresco and Seahurst Electric, has begun the conversion of the city-owned street lights to LEDs. Work will continue through the summer. Short term, temporary lane closures will be required.

 

Military Road South at S 298th Street – Compact Roundabout

Roundabout operations began March 19, 2019.

The Contractor will complete splitter island modifications and the permanent striping in two-three weeks (weather dependent).- Temporary lane closures will be required including alternating one-way traffic. Anticipate delays. More project information can be found at: https://www.cityoffederalway.com/streetsystems/capitalprojects/military298th

 

 

For additional capital project information visit: https://www.cityoffederalway.com/streetsystems/capitalprojects

 

 

Department: